NetClose - Auto-Generate Tasks

Overview

In NetClose, users have the option to automatically generate tasks on a scheduled basis. The settings to automatically generate a task can be found on each NetClose Task record. If there is a specific time that a user wants tasks generated, then they should create a new deployment of the NetClose | Task - Auto Generate | MR script and schedule it at the time they would like it to run. The time zone for the schedule will be based on the time zone of the user that set the scheduled script.

Video walkthrough

Step-by-step process

  1. To manually update the auto-generation fields on a task, navigate to the task template record via NetClose > Lists > Tasks.
  2. Filter the list to Close Task Templates Only and select Edit on the task template. 
  3. Populate an Auto Generation Day. This tells NetClose what day of the month the task should be automatically generated on. 
  4. Populate the Auto Generation Preferred Period. This tells NetClose what period this task should be associated with when it is automatically generated. See below for examples.

5. Save the task.

Task Auto Generation Examples

Example 1: Assume this example relates to calendar year-end. 

MOST COMMONLY USED EXAMPLE

  • Frequency: Monthly
  • Auto Generation Day: -1 
  • Auto Generation Preferred Period: Current
  • Preparer Due Date (Relative): 5
  • December tasks will be generated on Dec. 31st with a due date that is 5 business days after Dec. 31st.

Example 2: Assume this example relates to calendar year-end.

  • Frequency: Monthly
  • Auto Generation Day: 1
  • Auto Generation Preferred Period: Current
  • Preparer Due Date (Relative): 5
  • January tasks will be generated on Jan. 1st with a due date that is 5 business days from Jan. 31st.

Example 3: Assume this example relates to calendar year-end. 

  • Frequency: Monthly
  • Auto Generation Day: -1
  • Auto Generation Preferred Period: Next
  • Preparer Due Date (Relative): 5
  • January tasks will be generated on Dec. 31st with a due date that is 5 business days from Jan. 31st.

Example 4: Assume this example relates to calendar Q2. 

MOST COMMONLY USED EXAMPLE

  • Frequency: Quarterly
  • Auto Generation Day: -1
  • Auto Generation Preferred Period: Current
  • Preparer Due Date (Relative): 5
  • Q2 tasks will be generated on Jun. 30th (these will appear under your June period on your Task list/board) with a due date that is 5 business days from Jun. 30th.

Example 5: Assume this example relates to calendar Q2. 

  • Frequency: Quarterly
  • Auto Generation Day: 1
  • Auto Generation Preferred Period: Current
  • Preparer Due Date (Relative): 5
  • Q2 tasks will be generated on July 1st (these will appear under your July period on your Task list/board) with a due date that is 5 business days from July 31st. 

Example 6: Assume this example relates to calendar year-end. 

  • Frequency: Weekly
  • Weekday Due: Monday
  • Auto Generation Day: -1
  • Auto Generation Preferred Period: Next
  • Four Weekly January tasks (four Mondays in January) will be generated on Dec. 31st (these will appear under your January period on your Task list/board) with a due date for each Monday in the period. 